Hero Background

Kitchen Remodel Timeline: What Actually Happens Week by Week (2026 Guide)

Introduction

If you're searching for a kitchen remodel timeline, you're likely trying to answer one question: How disruptive is this really going to be? Many homeowners delay remodeling simply because they don't know what happens when—or how long they'll be without a functional kitchen.

This guide walks through what actually happens week by week during a kitchen remodel, based on how professional kitchen remodel contractors plan and execute projects in The Woodlands and surrounding areas.

Before diving into timelines, many homeowners first review how a full project is structured through a professional kitchen remodeling service to understand scope and responsibilities.

Overview: Typical Kitchen Remodel Timeline (Big Picture)

Most professionally managed kitchen remodels follow this general range:

  • Planning & design: 3–6 weeks
  • Construction phase: 6–10 weeks
  • Total project duration: 9–16 weeks

The exact timeline depends on layout changes, cabinetry type, permit requirements, and material lead times.

Phase 1: Planning, Design & Selections (Weeks 1–4)

The planning phase sets the foundation for the entire project. Rushing this phase almost always creates delays later.

Week 1: Initial Planning & Scope Definition

This is where the project truly begins. During this phase:

  • Layout goals are defined
  • Budget ranges are established
  • Existing conditions are evaluated
  • Preliminary design direction is set

Early coordination here prevents major delays later—especially when cabinetry, appliances, and lighting must work together.

Week 2: Design Development & Layout Finalization

Design details are refined:

  • Cabinet layouts are finalized
  • Appliance locations are locked
  • Electrical and plumbing needs are identified
  • Structural changes (if any) are confirmed

Cabinet decisions are especially critical at this stage. Many timeline delays happen when cabinetry is selected too late, which is why kitchens are often planned alongside custom cabinet design rather than as a last-minute choice.

Week 3–4: Permits, Engineering & Ordering

During this phase:

  • Permits are submitted (if required)
  • Structural or electrical engineering is completed
  • Cabinets, appliances, and long-lead materials are ordered

This phase is mostly administrative—but skipping or rushing it almost always causes construction delays.

Phase 2: Demolition & Rough Construction (Weeks 5–7)

This is when construction begins and the old kitchen is transformed.

Week 5: Demolition

The old kitchen is removed:

  • Cabinets and countertops are taken out
  • Flooring is removed if being replaced
  • Walls are opened if layout changes are planned

This is usually the most disruptive week. Most homeowners set up a temporary kitchen during this time.

Week 6: Structural, Electrical & Plumbing Work

This is where the "invisible" work happens:

  • New electrical circuits are installed
  • Plumbing lines are relocated or upgraded
  • Ventilation improvements are added
  • Structural framing is completed (if applicable)

This phase is required to pass inspections and ensure the kitchen performs safely long-term.

Week 7: Inspections & Drywall

After rough-ins:

  • Required inspections are completed
  • Drywall is installed and finished
  • Walls are prepped for cabinets and finishes

Any inspection failure here can pause the timeline—one reason experienced kitchen remodel contractors matter.

Phase 3: Cabinetry, Surfaces & Finishes (Weeks 8–10)

This is when the kitchen starts to look finished and functional again.

Week 8: Cabinet Installation

Cabinet installation is a major milestone:

  • Base and wall cabinets are installed
  • Islands and specialty units are set
  • Cabinet alignment and leveling is finalized

For kitchens using custom cabinetry, this phase often defines the overall quality of the remodel. Proper installation ensures durability and smooth operation for decades.

Week 9: Countertops, Flooring & Backsplash

During this stage:

  • Countertops are templated and installed
  • Flooring is completed (if not done earlier)
  • Backsplash installation begins

The kitchen now starts to look finished—but there's still important detail work ahead.

Week 10: Appliances, Lighting & Trim

Final components are installed:

  • Appliances are set and connected
  • Lighting fixtures are installed
  • Trim, hardware, and finishing details are completed

At this point, the kitchen is functional again.

Phase 4: Final Walkthrough & Completion (Weeks 11–12)

Final Inspections & Punch List

The project wraps up with:

  • Final inspections (if required)
  • Adjustments to doors, drawers, and hardware
  • Touch-ups and corrections
  • Final walkthrough with the homeowner

This phase ensures the kitchen performs as intended—not just that it looks good.

What Can Extend a Kitchen Remodel Timeline?

Common causes of delays include:

  • Late design changes
  • Cabinet or appliance backorders
  • Permit delays
  • Inspection rescheduling
  • Unplanned structural or electrical issues

Many of these risks are reduced when the project is planned holistically—often alongside cost planning guides like a detailed kitchen remodeling cost breakdown .

Can You Live at Home During a Kitchen Remodel?

In most cases, yes—but expect:

  • Temporary cooking arrangements
  • Limited access during work hours
  • Noise and dust during demolition and rough-in phases

Clear communication with your contractor helps set realistic expectations.

Why Timeline Transparency Matters When Choosing a Contractor

Reliable contractors don't just give a start date—they explain:

  • What happens each week
  • When decisions are required from you
  • How delays are handled
  • How coordination is managed

This level of clarity builds confidence and prevents frustration during construction.

Planning Your Next Step

If you're preparing for a remodel, start by understanding how kitchens are planned, built, and scheduled through a professional kitchen remodeling service . Coordinating cabinetry early through custom cabinet planning is one of the most effective ways to keep your project on schedule.

Kitchen planning and construction best practices align with guidance from the National Kitchen & Bath Association , which emphasizes early design coordination, clear sequencing, and contractor-led scheduling for predictable remodel timelines.

Ready to start planning your kitchen remodel? Contact our team or request a detailed timeline and estimate for your project.

Curious about our past work? View Select Remodeling & Construction on Google to see completed projects and testimonials.

Frequently Asked Questions

Most kitchen remodels take 9–16 weeks, including planning, permitting, and construction.

Cabinet fabrication and delivery often take the longest, especially for custom cabinetry.

Yes, but rushing often increases costs and risks mistakes. Proper planning saves more time overall.

Ideally during the design phase—before demolition begins.

Yes. Failed or delayed inspections can pause construction until issues are corrected.

No. The most disruptive period is typically during demolition and cabinet installation.

Yes. Moving plumbing, gas, or walls increases both time and cost.

Custom cabinets take longer to fabricate but usually result in better fit and fewer installation issues.

Finalize design decisions early, order materials on time, and work with experienced contractors.

During the planning phase—before locking selections or budgets.
Scroll to top
Call Ask Experts Email WhatsApp